Permit guide

Travis County Septic Permits (2026): Fees & Process

Verified against county records · updated August 2, 2026 · rules change — confirm with the agent before applying

A standard residential septic permit in unincorporated Travis County costs $712 plus a $10 state fee, or $1,262 for an engineer-designed system, which shallow or sloped Hill Country sites frequently require. A maintenance contract adds $249. Everything files online through the MyGovernmentOnline portal, with no paper path, but first you must answer the question that trips up more Travis County owners than any fee: who has jurisdiction over your property.

Who Issues Your Septic Permit in Travis County?

Travis County TNR permits on-site sewage facilities (OSSFs) outside city limits, but Austin Water regulates them inside the City of Austin’s jurisdiction, and the two have different rules and different fees.

Check the City of Austin Jurisdiction Web Map first. One rule catches people out: by Austin City Code, any property with water frontage on Lake Austin or its tributaries falls under city jurisdiction, however the lot or drainfield is arranged. Several small cities, West Lake Hills and Bee Cave among them, run their own programs, and the Lower Colorado River Authority (LCRA) covers designated lake zones.

Travis County TNR — Development Services (permit desk) 700 Lavaca St., Suite 540, Austin, TX 78701 · Mailing: P.O. Box 1748, Attn: Permits, Austin, TX 78701 Phone: (512) 854-4215 · Inspections: (512) 854-4438 Permit desk hours: Monday–Thursday, 9 a.m.–2 p.m. (closed Fridays, so plan around it)

What Does a Travis County Septic Permit Cost?

A conventional residential system runs $712 plus the $10 TCEQ state fee; an engineered system is $1,262 plus $10; both add $125 for every 500 gallons per day (GPD) above the first 500.

From the county’s FY2026 Development Related Fees Schedule, effective January 1, 2026:

Application type Fee
Private Sewage Permit (up to 500 GPD) $712
Private Sewage Permit (over 500 GPD) $712 + $125 per additional 500 GPD
Engineered Construction Permit (up to 500 GPD) $1,262
Engineered Construction Permit (over 500 GPD) $1,262 + $125 per additional 500 GPD
Engineered Adjustment Permit $500
Maintenance Contract Fee $249
TCEQ State Fee $10 per application
Septic Verification $92 per submission
Non-permit-related OSSF inspection $107 per inspection
Re-inspection (after the first free inspection) $200 per inspection
30-day extension (one time only) $137
Septic subdivision review $524 per plat + $63 per lot over 4 lots

Budget two more line items: the MyGovernmentOnline portal charges a non-refundable $7–$10 transaction fee, and a floodplain permit ($149 and up outside Austin’s extraterritorial jurisdiction, or ETJ) applies if any part of your lot sits in the regulated floodplain.

A warning about numbers you’ll find elsewhere. Search results commonly quote Travis County septic permits at “$285–$475.” Those are not permit fees but refund amounts from an expired watershed rebate program. The current fees are in the table above, from the county’s own FY2026 schedule.

How the Permit Process Works, Step by Step

Nine stages, all inside the county’s online portal: confirm jurisdiction, assemble a detailed site plan, create an account, apply, answer review comments, post the permit, then schedule inspections in sequence.

  1. Confirm jurisdiction on the Austin jurisdiction map. The county process covers only development outside the corporate city limits.
  2. Assemble your site plan. Travis asks for more than most: property lines and dimensions; all proposed structures, pools, driveways, paving, patios and decks; wells and septic systems within 150 feet including those on neighboring property; potable water lines; easements; creeks, ditches, ponds; all slopes of 15% or greater; floodplain status or an explicit statement that no part of the lot is in the floodplain; one-foot contours across the system area; and an erosion and sediment control plan.
  3. Collect the documents: the OSSF Soil Evaluation Form (SP-07); the Affidavit to Public (SP-04) if your system uses aerobic or advanced treatment or surface/drip irrigation; an Affidavit Linking Properties if the system crosses a property line; the maintenance contract where required; and a floor plan. The old checklist PDF is no longer a separate upload; its questions are built into the application now.
  4. Create a MyGovernmentOnline account at mgoconnect.org.
  5. Apply online, choosing Residential On-Site Wastewater (or the combined development/driveway variants).
  6. Track and respond in the portal. Review pauses until you answer each comment, which is where most delay comes from.
  7. Receive the permit by email, then post it somewhere visible from the public right-of-way before work starts.
  8. Schedule inspections in the portal before 2 p.m. the working day prior. Depending on system type, you may need Open Trench, Rock and Pipe, Tank/Pump/Alarm, Scarification, Landscaping, and Final.
  9. Submit the Designer Certification Letter after inspection to close out the file.

Ask about turnaround when you file, and never let a contractor break ground on the promise that the permit is coming.

The One Consumer Break Worth Knowing

Travis County refunds septic permit fees for qualifying repairs and replacements in the Gilleland Creek and Walnut Creek watershed areas. If your failing system sits in either watershed, ask about the waiver before you pay. It is real, and it is not advertised loudly.

Travis County Permit FAQs

What does the county charge for a Travis County septic permit?

$712 plus a $10 state fee for a standard residential system, or $1,262 plus $10 if the design is engineered; add $249 when a maintenance contract is required and $125 for every 500 GPD above the first 500. Budget the portal fee ($7–$10) and, where applicable, a floodplain permit.

Do I file with Travis County or the City of Austin?

Outside city limits, Travis County TNR; inside the City of Austin’s jurisdiction, Austin Water. Lake Austin water frontage puts you under the city however the lot is laid out, and filing with the wrong office costs you weeks.

How long does approval take?

Travis County does not publish a review turnaround. What we can tell you is where the clock stops: review pauses until you answer every reviewer comment, so incomplete site plans drive most delay.

Can I install my own septic system in Travis County?

Texas rules require licensed professionals for the site evaluation and installation, and the county requires a designer certification letter after inspection. Which credential Travis accepts for the designer of record is not published; we have asked, and will publish the answer once we have it in writing.

Sources & Methodology

Every fee here was read in Travis County’s own FY2026 schedule; anything we could not read cleanly was left out rather than estimated.

Two variance-related figures sat in a multi-column PDF block where row alignment could not be confirmed, so they stay out until the county confirms them. City of Austin fees are absent because the city’s fee PDF would not render.

  • Travis County TNR, FY2026 Development Related Fees Schedule, effective 01/01/2026, read July 30, 2026
  • Travis County TNR, Residential OSSF (Septic System) Permit page, accessed July 30, 2026
  • Travis County TNR, Septic Permit FAQ, accessed July 30, 2026
  • Austin Water, On-Site Sewage Facilities, City Code Ch. 15-5, accessed July 30, 2026
  • 30 TAC Chapter 285 (planning, construction, licensing standards)

Ground conditions and licensed providers: the Travis County septic hub. See also routine pumping costs and what an aerobic maintenance contract must contain.

Ready when you are

Get free quotes from verified septic pros.

Tell us once — we send it to up to 3 verified pros. Free, no spam, delete your request anytime.

Septic Quote Request

Secure form. Sent over an encrypted connection to up to 3 verified pros. Never sold to data brokers, and you can have your request deleted anytime.