Skip to content
Nearby Septic — nearbyseptic.com · Verified septic directory · printed Nov 24, 2026
Permit guide

Llano County Septic Permits (2026): County vs. LCRA

Verified against county records · page updated October 17, 2026 · rules change — confirm with the agent before applying

Two offices issue septic permits in Llano County. A county permit costs $225 (standard trench or tank), $350 (home aerobic, low-pressure or engineered design) or $450 (commercial), payable to Llano County Development Services; inside the Lower Colorado River Authority’s (LCRA) band around Lakes Buchanan, Inks, LBJ and Marble Falls, LCRA’s permit is $260 conventional or $410 if the design must come from an engineer or sanitarian. Neither office allows the state’s 10-acre exemption, and LCRA reinspects the septic system every time a lakeside property sells.

Is the lot inside LCRA’s lake zone?

Check LCRA’s jurisdiction first, because a lot near Lake Buchanan, Inks Lake, Lake LBJ or Lake Marble Falls belongs to LCRA, not the county. LCRA’s rules draw a Restricted Zone 200 feet back from each lake’s contour line (1,020 feet above sea level at Buchanan, 888 at Inks, 825 at LBJ, 738 at Marble Falls) and a Water Quality Zone running 2,000 feet past that. The 2,200-foot band is easier to check on LCRA’s address map than with a tape measure.

Everything else outside city limits is the county’s. In TCEQ’s 2025 report, the county authorized 77 systems and LCRA 74 inside Llano County, and the two approve different systems: 39 of the county’s 77 were standard trenches, while 35 of LCRA’s 74 were drip irrigation.

Cities complicate the line in three places:

  • Sunrise Beach Village’s development permit requires an “approved LCRA permit” for any septic installation.
  • Horseshoe Bay has its own number in TCEQ’s register, but as we read it on October 16, 2026, the city’s listing says its septic work is “administered by Counties and LCRA”: LCRA lists Horseshoe Bay among its cities, and the county covers the part of the city “outside LCRA jurisdiction.” LCRA’s March 2026 application names six cities and leaves Horseshoe Bay off. Start with LCRA’s map, and call the county at (325) 247-2039 if the address falls outside it.
  • The City of Llano runs a sewer system and had no listing of its own in TCEQ’s register when we read it on October 16, 2026. For a city lot without sewer service, ask the county first, which is what the register tells residents of an unlisted city to do.

Kingsland, Buchanan Dam and Tow are unincorporated, so the lake zone alone decides between LCRA and the county there. The Llano County directory page covers the county’s soils and both agencies’ system mix; LCRA’s program also reaches into Burnet County, where the same rules apply.

Fees side by side

The county’s septic permit fees run from $100 to $450 and LCRA’s from $260 to $410. LCRA footnotes that “$10 is added” for the state; the county says nothing about the state fee.

WorkLlano CountyLCRA (lake zone)
Standard or conventional system$225$260
Aerobic, low-pressure, engineered or professionally designed, single-family$350$410
Commercial$450$260 conventional, or $410 professionally designed for the first 500 gallons a day plus $45 per added 500
Repair$100 (non-major)Not separately listed
Reinspection when the property sellsNone listed$150 single-family, $100 commercial
Permit revision or renewalNone listed$50 each
Extra site tripNone listed$70

The county’s OSSF fee block is labeled only “Current,” with no adoption date (the posted file was created in March 2022), so confirm the amount before paying. The county also lists a floodplain development permit at $200 for a standard residence, and a $25 “LCRA Compliance Letter” that is free with a development permit. Starting development without the correct permit doubles the fee the county would normally charge. An old county septic package with 2005 fees ($310 aerobic, $410 commercial) still circulates online; those amounts are out of date. Other counties’ fees are in the Texas septic permit fee guide, and installed prices are in the new septic system cost guide.

The 10-acre exemption does not apply here

Both permitting offices require a septic permit on every tract, so the state’s 10-acre exemption is unavailable anywhere in Llano County outside city limits. State rule 30 TAC 285.3(f)(2) exempts a single home on 10 or more acres, but a county or river authority may be stricter.

The county’s 2018 Order says it “will permit and inspect all on-site systems regardless of the size of the tract of land the on-site system is situated upon.” TCEQ’s register still lists the county’s 1999 Order as current, and that one says the same thing: a permit is needed “regardless of acreage.” LCRA’s rules read: “Regardless of the lot or tract size, a permit is required prior to construction or installation of an on-site sewage facility within the LCRA’s jurisdiction.” The 10-acre rule guide explains where the exemption does work.

Getting a county permit: development permit first

Llano County ties the septic permit to its development and 911 process, so the first filing is the development application, not the septic design. The county’s 2021 development permit form says no work “may start” until the county issues a floodplain development permit or a Non-Floodplain Determination Card, and the permit expires if work does not begin within six months.

  1. File the development application through the county’s iWorQ portal. The county asks for 7 to 10 business days on non-floodplain determinations and says septic permits and floodplain development “may” take longer.
  2. Hire the site evaluator and designer. The county Order adopts the state’s Chapter 285 rules without adding its own credential limits, so state rules govern who may evaluate and design.
  3. Check the subdivision status. If the lot sits in a subdivision created after the county’s 2025 subdivision regulations and was never recorded, Development Services will not issue either permit. A new lot needs one acre without community water, or half an acre on a public water system, not counting easements and roads.
  4. Get the 911 address after the permits. The county assigns one only to a structure with its permits in hand; Horseshoe Bay addresses come from the city, (830) 598-8741.
  5. Pass inspection and receive approval before the system goes into use.

Lots subdivided before January 1, 1988 that fall short of the minimums can still be approved if the state’s separation distances can be met and a site evaluation supports the system.

Getting an LCRA permit: backhoe pits and a notarized form

LCRA wants its own soil form, two backhoe pits and a notarized application, and it will not schedule the site visit until the fee is paid.

  • Soil work: two backhoe pits at opposite ends of the proposed disposal area, logged on LCRA’s Soil Analysis form, left open for LCRA’s inspection. LCRA may require 24 hours between digging and analysis.
  • Paperwork: application signed by the owner before a notary, proof of ownership, scaled drawings, floor plans, a floodplain compliance acknowledgement or development permit from the local floodplain administrator, and a recorded plat for any lot under one acre.
  • Bedroom count: LCRA treats any room used for overnight sleeping as a bedroom “regardless of the presence or absence of a closet,” which can push a home into a larger system.
  • Restricted Zone: inside the 200-foot band, a system more than 75 feet from the top of the lake’s normal operating range must produce secondary-quality effluent, “such as an aerobic treatment unit, intermittently pressure dosed sand filter or other TCEQ approved method,” though three feet of suitable soil can substitute when used with low-pressure dosing. Closer than 75 feet, LCRA’s rule calls for “a facility as cited in Chapter 285 of the TCEQ Rules.”
  • Timing: LCRA’s FAQ tells applicants to allow up to 30 days from submission.

Applications go through LCRA’s online permitting portal or on paper; inspections are booked at 512-578-4091.

Selling a house on the lake: the reinspection

Every sale inside LCRA’s zone triggers a septic reinspection, and the seller’s permit to operate ends at transfer unless LCRA approves the system for continued use. The single-family fee is $150, and the Continued Use Authorization LCRA issues is good for six months. A system that uses a metal tank cannot be approved for continued use. LCRA posted a revised reinspection packet in May 2026 and says the older version stops being accepted on January 1, 2027.

The county has no comparable sale rule. Buyers anywhere in the county can still order a private inspection; prices are in the septic inspection cost guide.

Aerobic systems: a two-year contract, then different rules

Under both offices, a new aerobic system starts with a two-year maintenance contract; after that, LCRA lets a homeowner take over only after passing the state’s maintenance-technician training and test, or a homeowner equivalent TCEQ accepts. The county adds nothing to the state’s Chapter 285 rule, which lets a single-family owner either sign a new contract or maintain the system personally. LCRA’s section 10.12 requires the owner to submit proof of the training and test, then file the same reports a licensed provider would. LCRA also requires an electronic monitoring alarm on any secondary-treatment unit that feeds surface irrigation, serves a commercial system, or disposes of effluent within 75 feet of the lakes. What a service contract typically costs is covered in our aerobic maintenance contract guide.

Llano County septic forms and rules

The county posts its Order, fee schedule and subdivision regulations; LCRA posts its rules, fees and application packages.

Llano County septic permit FAQ

How much is a septic permit in Llano County?

A Llano County septic permit is $225 for a standard system, $350 for a residential aerobic or engineered system and $450 for commercial work. Inside LCRA’s lake zone the fee is $260 or $410; LCRA’s schedule notes that “$10 is added” for the state without saying whether it is inside those figures.

Do I need a septic permit on 10 acres in Llano County?

Yes, a permit is needed on any acreage in Llano County, from the county or from LCRA. Both the county Order and LCRA’s rules override the state exemption.

Who issues septic permits at Lake LBJ or Lake Buchanan?

LCRA issues septic permits within 2,200 feet of Lakes Buchanan, Inks, LBJ and Marble Falls. Its office is at 512-578-3216.

How long does a Llano County septic permit take?

Llano County asks for 7 to 10 business days on a non-floodplain determination and says septic permits may take longer. LCRA tells applicants to allow up to 30 days.

Does a septic inspection come with a home sale near the lakes?

Yes, LCRA reinspects the septic system at every sale in its zone, for $150 on a single-family home. The county has no such requirement.

Can I service my own aerobic system in Llano County?

Outside the lake zone, a single-family owner can maintain an aerobic system personally after the two-year contract ends. Inside it, LCRA first requires the state maintenance-technician training and test, or a TCEQ-accepted homeowner equivalent.

Sources & Methodology

We read every county and LCRA document named here on October 15, 2026, and re-read them on October 16. County fees come from its fee schedule PDF, process steps from its Development Services page, 2021 development form and 911 sheet, and lot rules from its May 2025 subdivision regulations. The 2018 Order is a scan; we quoted from our text recognition and checked the adoption date against the page image. Agent descriptions, the county office’s hours (weekdays 8 a.m. to 5 p.m.) and the 1999 Order are from TCEQ’s register of authorized agents, re-read on October 16, 2026.

LCRA’s zone lines, lot, bedroom, reinspection and maintenance rules come from its OSSF Rules (effective April 5, 2010); fees from its current fee page; process from its March 2026 application and May 2026 reinspection packet. System counts are from TCEQ’s 2025 report dated April 27, 2026. Left open: the county’s own septic application, whether either office’s fees include the state fee, and why LCRA’s application leaves Horseshoe Bay off its city list.

Authorities

Where to apply for a Llano County septic permit.

Llano County Authorized Agent

100 W SANDSTONE ST, STE 200A LLANO, TX, 78643
(325) 247-2039
Official OSSF septic permit information ↗

Before you start

Any new system or major repair needs authorization before construction starts. Emergency repair? Call the agent first — most offices fast-track failing-system fixes rather than letting sewage sit.

Hire a septic company in Llano County.

The license-verified septic companies on our Llano County page are each matched to TCEQ records, with phone numbers and license status.

Find Llano County septic companies
Free septic company quotes

Get free quotes from verified Llano County septic companies.

Pumping, an inspection, or help fixing a septic system: tell us once and we send it to up to 3 verified septic companies. Free, no spam, delete your request anytime.

Septic Quote Request

Secure form. Sent over an encrypted connection to up to 3 verified septic companies. Never sold to data brokers, and you can have your request deleted anytime.